  • “After more than two years of construction work and without a single lost-time injury, the Bjerkreim substation is now ready to be put into operation,” says Project Manager Even Vandbakk. The subst …

  • After almost two-and-a-half months of travelling by rail, sea and road, the first transformer has finally arrived at Statnett’s new substation in Bjerkreim, making the last 42 kilometres of its jou …

  • Siemens is currently working to establish the high-voltage plant with the pull-off and equipment framework at Bjerkreim Substation, now that Veidekke has completed the concrete structures and build …

  • The plot of land for Bjerkreim Sub Station has been prepared, and Siemens/Veidekke are now starting work on the station buildings and high voltage installations.

  • Today marks the start of the groundworks on the area of land for Bjerkreim Sub Station. Stangeland Maskin AS is carrying out the work, which it is estimated will take six months to complete.