Ørskog - Sogndal
New 420 kV power line between Ørskog and Sogndal

Statnett is building a new 420 kV power line between Ørskog in Møre og Romsdal and Fardal in Sogn og Fjordane to secure good power supply in Central Norway and strengthen the grid to realise new small-scale hydropower and renewable power production in Sunnmøre and in Sogn og Fjordane.

Central Norway (Nord-Trøndelag, Sør-Trøndelag and Møre og Romsdal) has an energy deficit of approx. 7 TWh (terawatt hours) over a normal year. 7 TWh corresponds to the annual consumption of 400,000 single-family homes with an average consumption of 20,000 kWh per year. When the energy deficit becomes so large, it means that the existing grid will be burdened even more and there will be a higher risk of faults. Shortage of capacity for new power generation

In Sogn og Fjordane and Sunnmøre the grid no longer has the capacity to absorb new power generation, i.e., small-scale hydropower plants and new renewable energy production will not be realised until new transmission lines are built. In Sogn og Fjordane alone, approx. 100 small-scale hydropower projects are awaiting processing by the Norwegian Water Resources and Energy Directorate (NVE). A new line between Ørskog and Fardal is the measure that is most robust for meeting future production and consumption changes in the region.

Published - Last updated
Planning

The project has now entered the planning phase. The following is important in this phase:

  • Identification of needs
  • Concept choice studies
  • External quality assurance

Statnett is responsible for planning and applying for the projects we believe to be socio-economically viable.

Licensing process

The project has now entered the licensing phase. A regular licensing process is currently structured as follows:

Planning proposal:

  • Statnett submits a planning proposal to the Norwegian Water Resources and Energy Directorate (NVE)
  • The NVE submits the proposal for public consultation

Licence application:

  • Statnett submits the application with enclosed impact assessments to the NVE
  • The NVE will organise the consultation, site inspection and public meetings
  • The NVE submits its recommendation to the Ministry of Petroleum and Energy (MPE)
  • The MPE submits the recommendation for consultation and makes a decision
  • The King in Council makes the final resolution

Appeals process:

  • Potential appeals from affected parties
  • The NVE considers the appeals and submits it to the MPE
  • The MPE settles the appeal
Construction

Construction ongoing.